Percentage | Payable on |
10% | Contract signature |
10% | Demolition Works |
10% | Construction Permits Acquisition |
10% | Finalization Of Shoring and Excavation Works |
10% | Reaching Ground Floor |
10% | Reaching 6th Floor |
10% | End Of Concrete Structure |
10% | Six months after finishing Concrete Structure |
10% | Delivery Of Units |